Published 2004-06-22 · Federal Register document 04-13700
Airworthiness Directives; Empresa Brasileira de Aeronautica S.A. (EMBRAER) Model EMB-120 Series Airplanes
Publication summary
This amendment adopts a new airworthiness directive (AD), applicable to certain EMBRAER Model EMB-120 series airplanes, that requires installing three new vertical cargo nets in cargo-configured cabins. This action is necessary to prevent significant movement of cargo during operation, which could result in loss of control of the airplane or injury to the flightcrew. This action is intended to address the identified unsafe condition.
Why this record is shown
Source: Federal Register annual FAA metadata. Acquired 2026-09-03T22:23:13.905821+00:00. The title, summary and date are source facts.
- Source revision
- federal_register_ad_metadata_2004-cb1e1f18d61cac01
- Source row
- results[285]
- Raw source SHA-256
- cb1e1f18d61cac01616802134d899b0c8ce1a9f79716b5ee037f78e4cb53a00a
Final-rule publication
Recorded publication clauses
- AD identifier printed in this edition
- 2004-12-18
- Effective date printed in this edition
- 2004-07-27
Some source clauses remain unstructured. Read the complete publication for conditions that have not been interpreted here.
Read 2 complete recorded clauses
Applicability wording · Applicability
Applicability: Model EMB-120 series airplanes, as listed in EMBRAER Service Bulletin 120-25-0255, dated March 5, 2002; and EMBRAER Service bulletin 120-25-0257, dated April 30, 2002; certificated in any category.
Exact source excerpt. Text positions 6397–6617, end exclusive, in the original decoded publication. SHA-256: 2ebf7b71310747871eb4800ba11d4a4de800adbfa4c269feaf8c3ee96a5ccf36
Compliance and requirements
Compliance: Required as indicated, unless accomplished
previously.
To prevent significant movement of cargo during operations,
which could result in loss of control of the airplane or injury to
the flightcrew, accomplish the following:
Installation
(a) Within 30 days after the effective date of this AD: Install
three new vertical cargo nets by doing all the actions in and per
the Accomplishment Instructions of EMBRAER Service Bulletin 120-25-
0255, dated March 5, 2002; or EMBRAER Service Bulletin 120-25-0257,
dated April 30, 2002; as applicable.
[[Page 34557]]
Alternative Methods of Compliance
(b) In accordance with 14 CFR 39.19, the Manager, International
Branch, ANM-116, FAA, Transport Airplane Directorate, is authorized
to approve alternative methods of compliance for this AD.
Incorporation by Reference
(c) The actions shall be done in accordance with EMBRAER Service
Bulletin 120-25-0255, dated March 5, 2002; or EMBRAER Service
Bulletin 120-25-0257, dated April 30, 2002; as applicable. This
incorporation by reference was approved by the Director of the
Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part
51. Copies may be obtained from Empresa Brasileira de Aeronautica
S.A. (EMBRAER), P.O. Box 343-CEP 12.225, Sao Jose dos Campos--SP,
Brazil. Copies may be inspected at the FAA, Transport Airplane
Directorate, 1601 Lind Avenue, SW., Renton, Washington; or at the
National Archives and Records Administration (NARA). For information
on the availability of this material at NARA, call (202) 741-6030,
or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
Note 1: The subject of this AD is addressed in Brazilian
airworthiness directive 2001-02-02R1, dated April 22, 2003.
Effective Date
(d) This amendment becomes effective on July 27, 2004.
Exact source excerpt. Text positions 6617–8498, end exclusive, in the original decoded publication. SHA-256: 954cce4df5de9745ab97e484a105a1a49ef4feabbc9789ea8b1268017bd2f34b
No replacement link has been established from this edition. The complete historical rule chain and current legal effect remain unknown.
Find all recorded historical references to AD 2004-12-18 · 0 printed reference observations in this pinned collection.
These are observations from one dated publication. Current legal status is unknown; aircraft applicability, installed configuration, compliance and burden require separate evidence. Missing or unparsed conditions remain unknown.
Why these observations are shown
They were extracted offline from the same immutable official HTML source as the complete recorded text. The dated source wording, original text coordinates and exact quote digests are retained. PDF/text agreement and current regulatory effect have not been qualified.
Observation revision: whole-ad-publication-clause-observations-1.0.1. Text SHA-256: aa9b48b9e749429de58b177d799656622b81dbaed857cbeb9277134d7428f9e0. Source manifest: 809be655560ce867519f951a62decc9c495a5d8ca0d25bdf5a61f5eb7ffdd446.
Official source · 2004-06-22
Publication text
This is the complete recorded text of this dated publication.
Current legal effect is unknown. Aircraft applicability, installed configuration and compliance require separate evidence. PDF/text agreement has not been evaluated.
Read the complete official publication text
[Federal Register Volume 69, Number 119 (Tuesday, June 22, 2004)]
[Rules and Regulations]
[Pages 34556-34557]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 04-13700]
[[Page 34556]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
14 CFR Part 39
[Docket No. 2003-NM-96-AD; Amendment 39-13679; AD 2004-12-18]
RIN 2120-AA64
Airworthiness Directives; Empresa Brasileira de Aeronautica S.A.
(EMBRAER) Model EMB-120 Series Airplanes
AGENCY: Federal Aviation Administration, DOT.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: This amendment adopts a new airworthiness directive (AD),
applicable to certain EMBRAER Model EMB-120 series airplanes, that
requires installing three new vertical cargo nets in cargo-configured
cabins. This action is necessary to prevent significant movement of
cargo during operation, which could result in loss of control of the
airplane or injury to the flightcrew. This action is intended to
address the identified unsafe condition.
DATES: Effective July 27, 2004.
The incorporation by reference of certain publications listed in
the regulations is approved by the Director of the Federal Register as
of July 27, 2004.
ADDRESSES: The service information referenced in this AD may be
obtained from Empresa Brasileira de Aeronautica S.A. (EMBRAER), P.O.
Box 343-CEP 12.225, Sao Jose dos Campos--SP, Brazil. This information
may be examined at the Federal Aviation Administration (FAA), Transport
Airplane Directorate, Rules Docket, 1601 Lind Avenue, SW., Renton,
Washington; or at the National Archives and Records Administration
(NARA). For information on the availability of this material at NARA,
call (202) 741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
FOR FURTHER INFORMATION CONTACT: Todd Thompson, Aerospace Engineer,
International Branch, ANM-116, FAA, Transport Airplane Directorate,
1601 Lind Avenue, SW., Renton, Washington 98055-4056; telephone (425)
227-1175; fax (425) 227-1149.
SUPPLEMENTARY INFORMATION: A proposal to amend part 39 of the Federal
Aviation Regulations (14 CFR part 39) to include an airworthiness
directive (AD) that is applicable to certain EMBRAER Model EMB-120
series airplanes was published in the Federal Register on April 6, 2004
(69 FR 17991). That action proposed to require installing three new
vertical cargo nets in cargo-configured cabins.
Comments
Interested persons have been afforded an opportunity to participate
in the making of this amendment. No comments were submitted in response
to the proposal or the FAA's determination of the cost to the public.
Conclusion
The FAA has determined that air safety and the public interest
require the adoption of the rule as proposed.
Cost Impact
The FAA estimates that 153 airplanes of U.S. registry will be
affected by this AD, that it will take approximately 5 work hours per
airplane to accomplish the required installation, and that the average
labor rate is $65 per work hour. Required parts will cost between
$2,250 and $4,570, depending on the configuration of the airplane.
Based on these figures, the cost impact of the AD on U.S. operators is
estimated to be between $393,975 and $748,935, or between $2,575 and
$4,895 per airplane.
The cost impact figure discussed above is based on assumptions that
no operator has yet accomplished any of the requirements of this AD
action, and that no operator would accomplish those actions in the
future if this AD were not adopted. The cost impact figures discussed
in AD rulemaking actions represent only the time necessary to perform
the specific actions actually required by the AD. These figures
typically do not include incidental costs, such as the time required to
gain access and close up, planning time, or time necessitated by other
administrative actions.
Currently, there are no affected ``CTA Version'' airplanes on the
U.S. Register (as listed in the applicability of EMBRAER Service
Bulletin 120-25-0257, dated April 30, 2002). However, if an affected
airplane is imported and placed on the U.S. Register in the future, the
required actions will take about 9 work hours, at an average labor rate
of $65 per work hour. Required parts will cost about $6,663 per
airplane. Based on these figures, we estimate the cost of this AD to be
$7,248 per airplane.
Regulatory Impact
The regulations adopted herein will not have a substantial direct
effect on the States, on the relationship between the national
Government and the States, or on the distribution of power and
responsibilities among the various levels of government. Therefore, it
is determined that this final rule does not have federalism
implications under Executive Order 13132.
For the reasons discussed above, I certify that this action (1) is
not a ``significant regulatory action'' under Executive Order 12866;
(2) is not a ``significant rule'' under DOT Regulatory Policies and
Procedures (44 FR 11034, February 26, 1979); and (3) will not have a
significant economic impact, positive or negative, on a substantial
number of small entities under the criteria of the Regulatory
Flexibility Act. A final evaluation has been prepared for this action
and it is contained in the Rules Docket. A copy of it may be obtained
from the Rules Docket at the location provided under the caption
ADDRESSES.
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by
reference, Safety.
Adoption of the Amendment
0
Accordingly, pursuant to the authority delegated to me by the
Administrator, the Federal Aviation Administration amends part 39 of
the Federal Aviation Regulations (14 CFR part 39) as follows:
PART 39--AIRWORTHINESS DIRECTIVES
0
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. 106(g), 40113, 44701.
Sec. 39.13 [Amended]
0
2. Section 39.13 is amended by adding the following new airworthiness
directive:
2004-12-18 Empresa Brasileira De Aeronautica S.A. (EMBRAER):
Amendment 39-13679. Docket 2003-NM-96-AD.
Applicability: Model EMB-120 series airplanes, as listed in
EMBRAER Service Bulletin 120-25-0255, dated March 5, 2002; and
EMBRAER Service bulletin 120-25-0257, dated April 30, 2002;
certificated in any category.
Compliance: Required as indicated, unless accomplished
previously.
To prevent significant movement of cargo during operations,
which could result in loss of control of the airplane or injury to
the flightcrew, accomplish the following:
Installation
(a) Within 30 days after the effective date of this AD: Install
three new vertical cargo nets by doing all the actions in and per
the Accomplishment Instructions of EMBRAER Service Bulletin 120-25-
0255, dated March 5, 2002; or EMBRAER Service Bulletin 120-25-0257,
dated April 30, 2002; as applicable.
[[Page 34557]]
Alternative Methods of Compliance
(b) In accordance with 14 CFR 39.19, the Manager, International
Branch, ANM-116, FAA, Transport Airplane Directorate, is authorized
to approve alternative methods of compliance for this AD.
Incorporation by Reference
(c) The actions shall be done in accordance with EMBRAER Service
Bulletin 120-25-0255, dated March 5, 2002; or EMBRAER Service
Bulletin 120-25-0257, dated April 30, 2002; as applicable. This
incorporation by reference was approved by the Director of the
Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part
51. Copies may be obtained from Empresa Brasileira de Aeronautica
S.A. (EMBRAER), P.O. Box 343-CEP 12.225, Sao Jose dos Campos--SP,
Brazil. Copies may be inspected at the FAA, Transport Airplane
Directorate, 1601 Lind Avenue, SW., Renton, Washington; or at the
National Archives and Records Administration (NARA). For information
on the availability of this material at NARA, call (202) 741-6030,
or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
Note 1: The subject of this AD is addressed in Brazilian
airworthiness directive 2001-02-02R1, dated April 22, 2003.
Effective Date
(d) This amendment becomes effective on July 27, 2004.
Issued in Renton, Washington, on June 9, 2004.
Kalene C. Yanamura,
Acting Manager, Transport Airplane Directorate, Aircraft Certification
Service.
[FR Doc. 04-13700 Filed 6-21-04; 8:45 am]
BILLING CODE 4910-13-P
Why this text is shown
The complete text was extracted from the official GovInfo HTML edition for this publication. Acquired 2026-10-09T04:04:04.654844+00:00. Text extraction preserves the recorded source wording; it does not determine current requirements.
Open the captured official edition
- Source SHA-256
- 16a9ed8ffdeac0f18b82f76ca87e916d1626f9c6d7189caf869cc8b378e8e880
- Text SHA-256
- aa9b48b9e749429de58b177d799656622b81dbaed857cbeb9277134d7428f9e0
Return to the full metadata catalog · Search complete publication text · Explore retained publication text and evidence
Coverage and limits
These are dated publication metadata, recorded clauses and literal source observations. Word, model-label, header and reference matches do not establish current legal effect, manufacturer/model identity, aircraft applicability, installed configuration or compliance.
The collection uses 33 explicit annual source snapshots. Source captures and operative-text qualifications have separate states. Missing information remains unknown.