Published 2025-02-04 · Federal Register document 2025-02147
Airworthiness Directives; Bombardier, Inc., Airplanes
Publication summary
The FAA is superseding Airworthiness Directive (AD) 2021-10- 02, which applied to all Bombardier, Inc., Model BD-700-1A10 and BD- 700-1A11 airplanes. AD 2021-10-02 required repetitive general visual inspections of the left- and right-hand elevator torque tube bearings for any sand, dust, or corrosion; repetitive functional tests of the elevator control system; and replacement of the elevator torque tube bearings if necessary. This AD continues to require certain actions in AD 2021-10-02 and requires revising the existing maintenance or inspection program, as applicable, to incorporate a new airworthiness limitation. This AD was prompted by a determination that a new airworthiness limitation is necessary. The FAA is issuing this AD to address the unsafe condition on these products.
Why this record is shown
Source: Federal Register annual FAA metadata. Acquired 2026-09-03T22:24:20.413248+00:00. The title, summary and date are source facts.
- Source revision
- federal_register_ad_metadata_2025-67d39c2af9a91434
- Source row
- results[24]
- Raw source SHA-256
- 67d39c2af9a914349adee3ee1cee836da6415ed54d2b01123da75b563b687ab0
Final-rule publication
Recorded publication clauses
- AD identifier printed in this edition
- 2024-26-09
- Effective date printed in this edition
- 2025-03-11
Read 14 complete recorded clauses
Effective Date
(a) Effective Date
This airworthiness directive (AD) is effective March 11, 2025.
[[Page 8899]]
Exact source excerpt. Text positions 15375–15478, end exclusive, in the original decoded publication. SHA-256: 1ad25c4fc69aeef83d6b30492c40e2af18e1d555fc4d3ccc08b60994b9aad660
Affected ADs
(b) Affected ADs
This AD replaces AD 2021-10-02, Amendment 39-21535 (86 FR 33088,
June 24, 2021) (AD 2021-10-02).
Exact source excerpt. Text positions 15478–15599, end exclusive, in the original decoded publication. SHA-256: dd3d136772c98ef78babc2f2f9716ba796bd63892bfa4f6d52f8a907bd2f8f63
Applicability wording · Applicability
(c) Applicability
This AD applies to Bombardier, Inc., Model BD-700-1A10 and BD-
700-1A11 airplanes, certificated in any category, having serial
numbers 9002 through 60081 inclusive.
Exact source excerpt. Text positions 15599–15789, end exclusive, in the original decoded publication. SHA-256: a5ddc9bf8227e6fcaa91a6179e5b47fea8b03017041534b469bda3a33d55710e
Subject
(d) Subject
Air Transport Association (ATA) of America Code 05, Time Limits/
Maintenance Checks; 27, Flight Controls.
Exact source excerpt. Text positions 15789–15913, end exclusive, in the original decoded publication. SHA-256: 2a4d2e59e5260f0123c7ef2a48c21e2ea2be1893b6e6e6544ea8d4c08b758fef
Reason
(e) Reason
This AD was prompted by a determination that a new airworthiness
limitation is necessary. The FAA is issuing this AD to address sand
contamination and corrosion of the elevator torque tube bearings,
which could lead to binding or seizure of the bearings, and
potentially lead to a reduction in or loss of airplane pitch
control.
Exact source excerpt. Text positions 15913–16264, end exclusive, in the original decoded publication. SHA-256: 2ebc87a48a7f6b71e427da8f7f3dcdf30f20f0186b76520f5477c403ca70dfdf
Compliance
(f) Compliance
Comply with this AD within the compliance times specified,
unless already done.
Exact source excerpt. Text positions 16264–16366, end exclusive, in the original decoded publication. SHA-256: 00fbfa31932483f627d0ce0a11cbd2e35e15d9231842b91ac85623ce533912d3
Retained Inspection and Corrective Actions, With Change
(g) Retained Inspection and Corrective Actions, With Change
This paragraph restates the requirements of paragraph (g) of AD
2021-10-02, with a change to table 1 to paragraph (g), which
identifies the airplane marketing designation instead of the serial
number range, and a change to add an additional source for
identifying the date of airplane manufacture. Within 36 months from
July 29, 2021 (the effective date of AD 2021-10-02) or within 63
months from the date of airplane manufacture, as identified on the
identification data plate of the airplane or in the airplane
technical logbook, whichever occurs later: Do a general visual
inspection of the left- and right-hand elevator torque tube bearings
for any sand, dust, or corrosion; perform a functional test of the
elevator control system; and do all applicable corrective actions;
in accordance with the Accomplishment Instructions of paragraphs
2.B., 2.C., and 2.D. of the applicable material specified in table 1
to paragraph (g) of this AD. Applicable corrective actions must be
done before further flight. Repeat the general visual inspection and
functional test thereafter at intervals not to exceed 63 months.
Accomplishing the revision of the existing maintenance or inspection
program required by paragraph (i) of this AD terminates the
requirements of this paragraph.
Table 1 to Paragraph (g)--Service Information
[GRAPHIC] [TIFF OMITTED] TR04FE25.000
Exact source excerpt. Text positions 16366–17811, end exclusive, in the original decoded publication. SHA-256: 0012e40abe31260fa2851a347879de5d59ae2c71d8d11b7f7fc48fb3cbc8faf0
No Reporting Requirement
(h) No Reporting Requirement
Although the material identified in table 1 to paragraph (g) of
this AD specifies to submit certain information to the manufacturer,
this AD does not include that requirement.
Exact source excerpt. Text positions 17811–18024, end exclusive, in the original decoded publication. SHA-256: 49ef1b82834b8f2effb35d7fc46ba33e4914a8984f20c4e66a0e00b5dba700e5
New Revision of the Existing Maintenance or Inspection Program
(i) New Revision of the Existing Maintenance or Inspection Program
Within 30 days after the effective date of this AD, revise the
existing maintenance or inspection program, as applicable, to
incorporate the information specified in the applicable temporary
revision identified in table 2 to paragraph (i) of this AD. The
initial compliance time for doing the task is at the time specified
in the applicable temporary revision identified in table 2 to
paragraph (i) of this AD, or within 90 days after the effective date
of this AD, whichever occurs later. Accomplishing the revision of
the existing maintenance or inspection program required by this
paragraph terminates the actions required by paragraph (g) of this
AD.
[[Page 8900]]
Table 2 to Paragraph (i)--Applicable Temporary Revisions
[GRAPHIC] [TIFF OMITTED] TR04FE25.001
Exact source excerpt. Text positions 18024–18873, end exclusive, in the original decoded publication. SHA-256: 85f8be65fdbf55deaf9d2b00bdd6f0cf694b11c4798e6e276bc02245b1de2213
New No Alternative Actions or Intervals
(j) New No Alternative Actions or Intervals
After the existing maintenance or inspection program has been
revised as required by paragraph (i) of this AD, no alternative
actions (e.g., inspections) or intervals may be used unless the
actions and intervals are approved as an alternative method of
compliance (AMOC) in accordance with the procedures specified in
paragraph (l)(1) of this AD.
Exact source excerpt. Text positions 18873–19275, end exclusive, in the original decoded publication. SHA-256: 1de22ddaa52e3ff6d5601f4829dcd4efbc68f945849d1c23e4b7cd70f257a00a
Credit for Previous Actions
(k) Credit for Previous Actions
(1) This paragraph provides credit for actions required by
paragraph (g) of this AD, if those actions were performed before
July 29, 2021 (the effective date of AD 2021-10-02) using the
applicable material specified in paragraphs (k)(1)(i) through (vi)
of this AD, which are not incorporated by reference in this AD.
(i) Bombardier Service Bulletin 700-1A11-27-041, dated July 23,
2020.
(ii) Bombardier Service Bulletin 700-27-083, dated July 23,
2020.
(iii) Bombardier Service Bulletin 700-27-5012, dated July 23,
2020.
(iv) Bombardier Service Bulletin 700-27-5503, dated July 23,
2020.
(v) Bombardier Service Bulletin 700-27-6012, dated July 23,
2020.
(vi) Bombardier Service Bulletin 700-27-6503, dated July 23,
2020.
(2) This paragraph provides credit for the initial and
repetitive inspection actions required by paragraph (i) of this AD
if those actions were performed before the effective date of this AD
using the applicable material identified in table 1 to paragraph (g)
of this AD, which were incorporated by reference in AD 2021-10-02.
Exact source excerpt. Text positions 19275–20403, end exclusive, in the original decoded publication. SHA-256: c40fa1b5aa686f867b05a2ac41205fbab56bbdf12052e79bfdb0356e9929798d
Additional AD Provisions
(l) Additional AD Provisions
The following provisions also apply to this AD:
(1) Alternative Methods of Compliance (AMOCs): The Manager,
International Validation Branch, FAA, has the authority to approve
AMOCs for this AD, if requested using the procedures found in 14 CFR
39.19. In accordance with 14 CFR 39.19, send your request to your
principal inspector or responsible Flight Standards Office, as
appropriate. If sending information directly to the manager of the
International Validation Branch, mail it to the address identified
in paragraph (m)(1) of this AD. Information may be emailed to:
[email protected].
(i) Before using any approved AMOC, notify your appropriate
principal inspector, or lacking a principal inspector, the manager
of the responsible Flight Standards Office.
(ii) AMOCs approved previously for AD 2021-10-02, are approved
as AMOCs for the corresponding provisions of paragraph (g) of this
AD.
(2) Contacting the Manufacturer: For any requirement in this AD
to obtain instructions from a manufacturer, the instructions must be
accomplished using a method approved by the Manager, International
Validation Branch, FAA; or Transport Canada; or Bombardier, Inc.'s
Transport Canada Design Approval Organization (DAO). If approved by
the DAO, the approval must include the DAO-authorized signature.
Exact source excerpt. Text positions 20403–21765, end exclusive, in the original decoded publication. SHA-256: ba8dac1ee948695a929aa12409f05bc54ca5081119d18935ea645cb6f4743b4b
Additional Information
(m) Additional Information
(1) For more information about this AD, contact Gabriel Kim,
Aviation Safety Engineer, FAA, 1600 Stewart Avenue, Suite 410,
Westbury, NY 11590; telephone 516-228-7300; email [email protected].
(2) Material identified in this AD that is not incorporated by
reference is available at the address specified in paragraph (n)(5)
of this AD.
Exact source excerpt. Text positions 21765–22142, end exclusive, in the original decoded publication. SHA-256: 0e61d1adc56523ed1fc3a1e31f5f437343aef6131383e78418a11dd9d5b0046e
Material Incorporated by Reference
(n) Material Incorporated by Reference
(1) The Director of the Federal Register approved the
incorporation by reference (IBR) of the material listed in this
paragraph under 5 U.S.C. 552(a) and 1 CFR part 51.
(2) You must use this material as applicable to do the actions
required by this AD, unless this AD specifies otherwise.
(3) The following material was approved for IBR on March 11,
2025.
(i) (Bombardier) Global 5500, GL 5500 Time Limits/Maintenance
Checks Temporary Revision, 5-2-3, dated March 31, 2023.
(ii) (Bombardier) Global 6500, GL 6500 Time Limits/Maintenance
Checks Temporary Revision 5-2-3, dated March 31, 2023.
(iii) Bombardier Global 5000, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-21, dated March 31, 2023.
(iv) Bombardier Global 5000, GL 5000 Featuring Global Vision
Flight Deck Time Limits/Maintenance Checks Temporary Revision 5-2-
20, dated March 31, 2023.
(v) Bombardier Global 6000, GL 6000 Time Limits/Maintenance
Checks Temporary Revision 5-2-20, dated March 31, 2023.
[[Page 8901]]
(vi) Bombardier Global Express, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-53, dated March 31, 2023.
(vii) Bombardier Global Express XRS, BD-700 Time Limits/
Maintenance Checks Temporary Revision 5-2-15, dated March 31, 2023.
(4) The following material was approved for IBR on July 29, 2021
(86 FR 33088, June 24, 2021).
(i) Bombardier Service Bulletin 700-1A11-27-041, Revision 1,
dated December 7, 2020.
(ii) Bombardier Service Bulletin 700-27-083, Revision 1, dated
December 7, 2020.
(iii) Bombardier Service Bulletin 700-27-5012, Revision 1, dated
December 7, 2020.
(iv) Bombardier Service Bulletin 700-27-5503, Revision 1, dated
December 7, 2020.
(v) Bombardier Service Bulletin 700-27-6012, Revision 1, dated
December 7, 2020.
(vi) Bombardier Service Bulletin 700-27-6503, Revision 1, dated
December 7, 2020.
(5) For Bombardier material identified in this AD, contact
Bombardier Business Aircraft Customer Response Center, 400
C[ocirc]te-Vertu Road West, Dorval, Qu[eacute]bec H4S 1Y9, Canada;
telephone 514-855-2999; email bombardier.com">ac.yul@aero.bombardier.com; website
bombardier.com.
(6) You may view this material at the FAA, Airworthiness
Products Section, Operational Safety Branch, 2200 South 216th St.,
Des Moines, WA. For information on the availability of this material
at the FAA, call 206-231-3195.
(7) You may view this material at the National Archives and
Records Administration (NARA). For information on the availability
of this material at NARA, visit www.archives.gov/federal-register/cfr/ibr-locations or email [email protected].
Exact source excerpt. Text positions 22142–24863, end exclusive, in the original decoded publication. SHA-256: c86f81fccb95f7a70616ab8fc4a31c2e94ad96af030d0a0583bbfdb61eca8dc4
Explicit historical replacement wording
Find all recorded historical references to AD 2024-26-09 · 0 printed reference observations in this pinned collection.
These are observations from one dated publication. Current legal status is unknown; aircraft applicability, installed configuration, compliance and burden require separate evidence. Missing or unparsed conditions remain unknown.
Why these observations are shown
They were extracted offline from the same immutable official HTML source as the complete recorded text. The dated source wording, original text coordinates and exact quote digests are retained. PDF/text agreement and current regulatory effect have not been qualified.
Observation revision: whole-ad-publication-clause-observations-1.0.1. Text SHA-256: 42b77dd57973e73286d34f154b19847998b50bbc8f758baa8d44169b16bb6f03. Source manifest: 481b7ce940f7521db5d83e0659b37b611292d3a9f90c20077311973216fbd808.
Official source · 2025-02-04
Publication text
This is the complete recorded text of this dated publication.
Current legal effect is unknown. Aircraft applicability, installed configuration and compliance require separate evidence. PDF/text agreement has not been evaluated.
Read the complete official publication text
[Federal Register Volume 90, Number 22 (Tuesday, February 4, 2025)]
[Rules and Regulations]
[Pages 8896-8901]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-02147]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
14 CFR Part 39
[Docket No. FAA-2024-1483; Project Identifier MCAI-2023-01094-T;
Amendment 39-22924; AD 2024-26-09]
RIN 2120-AA64
Airworthiness Directives; Bombardier, Inc., Airplanes
AGENCY: Federal Aviation Administration (FAA), DOT.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The FAA is superseding Airworthiness Directive (AD) 2021-10-
02, which applied to all Bombardier, Inc., Model BD-700-1A10 and BD-
700-1A11 airplanes. AD 2021-10-02 required repetitive general visual
inspections of the left- and right-hand elevator torque tube bearings
for any sand, dust, or corrosion; repetitive functional tests of the
elevator control system; and replacement of the elevator torque tube
bearings if necessary. This AD continues to require certain actions in
AD 2021-10-02 and requires revising the existing maintenance or
inspection program, as applicable, to incorporate a new airworthiness
limitation. This AD was prompted by a determination that a new
airworthiness limitation is necessary. The FAA is issuing this AD to
address the unsafe condition on these products.
DATES: This AD is effective March 11, 2025.
The Director of the Federal Register approved the incorporation by
reference of certain publications listed in this AD as of March 11,
2025.
The Director of the Federal Register approved the incorporation by
reference of certain other publications listed in this AD as of July
29, 2021 (86 FR 33088, June 24, 2021).
ADDRESSES:
AD Docket: You may examine the AD docket at regulations.gov under
Docket No. FAA-2024-1483; or in person at Docket Operations between 9
a.m. and 5 p.m., Monday through Friday, except Federal holidays. The AD
docket contains this final rule, the mandatory continuing airworthiness
information (MCAI), any comments received, and other information. The
address for Docket Operations is U.S. Department of Transportation,
Docket Operations, M-30, West Building Ground Floor, Room W12-140, 1200
New Jersey Avenue SE, Washington, DC 20590.
Material Incorporated by Reference:
<bullet> For Bombardier material identified in this AD, contact
Bombardier Business
[[Page 8897]]
Aircraft Customer Response Center, 400 C[ocirc]te-Vertu Road West,
Dorval, Qu[eacute]bec H4S 1Y9, Canada; telephone 514-855-2999; email
bombardier.com">ac.yul@aero.bombardier.com; website bombardier.com.
<bullet> You may view this material at the FAA, Airworthiness
Products Section, Operational Safety Branch, 2200 South 216th St., Des
Moines, WA. For information on the availability of this material at the
FAA, call 206-231-3195. It is also available at regulations.gov under
Docket No. FAA-2024-1483.
FOR FURTHER INFORMATION CONTACT: Gabriel Kim, Aviation Safety Engineer,
FAA, 1600 Stewart Avenue, Suite 410, Westbury, NY 11590; telephone 516-
228-7300; email [email protected].
SUPPLEMENTARY INFORMATION:
Background
The FAA issued a notice of proposed rulemaking (NPRM) to amend 14
CFR part 39 to supersede AD 2021-10-02, Amendment 39-21535 (86 FR
33088, June 24, 2021) (AD 2021-10-02). AD 2021-10-02 applied to all
Bombardier, Inc., Model BD-700-1A10 and BD-700-1A11 airplanes. AD 2021-
10-02 required repetitive general visual inspections of the left- and
right-hand elevator torque tube bearings for any sand, dust, or
corrosion; repetitive functional tests of the elevator control system;
and replacement of the elevator torque tube bearings if necessary. The
FAA issued AD 2021-10-02 to address sand contamination and corrosion of
the elevator torque tube bearings, which could lead to binding or
seizure of the bearings, and potentially lead to a reduction in or loss
of airplane pitch control.
The NPRM published in the Federal Register on June 12, 2024 (89 FR
49819). The NPRM was prompted by AD CF-2020-29R1, dated October 20,
2023, issued by Transport Canada, which is the aviation authority for
Canada (Transport Canada AD CF-2020-29R1) (also referred to as the
MCAI). The MCAI states that data collected from the reports mandated by
Transport Canada AD CF-2020-29, dated August 21, 2020, was used to
validate inspection intervals, which have been integrated into new
certification maintenance requirement (CMR) tasks. The MCAI also states
that Transport Canada AD CF-2020-29R1 mandates the new CMR tasks while
giving credit for initial and repetitive inspections already performed,
revises the applicability to exclude airplanes delivered with the new
CMRs, and removes the reporting requirement.
In the NPRM, the FAA proposed to continue to require certain
actions in AD 2021-10-02. In the NPRM, the FAA also proposed to require
revising the existing maintenance or inspection program, as applicable,
to incorporate a new airworthiness limitation. The FAA is issuing this
AD to address sand contamination and corrosion of the elevator torque
tube bearings, which could lead to binding or seizure of the bearings,
and potentially lead to a reduction in or loss of airplane pitch
control.
You may examine the MCAI in the AD docket at regulations.gov under
Docket No. FAA-2024-1483.
Discussion of Final Airworthiness Directive
Comments
The FAA received a comment from an anonymous commenter who
supported the NPRM without change.
The FAA received an additional comment from Bombardier. The
following presents the comment received on the NPRM and the FAA's
response to that comment.
Request for Alternative Source of Airplane Date of Manufacture
Bombardier requested a revision to paragraph (g) of the proposed AD
to accommodate airplanes on which the identification data plate no
longer specifies the date of manufacture. Bombardier stated that, for
airplanes with serial numbers 60042 and 60045 and subsequent, the
airplane identification data plate no longer specifies the date of
manufacture. Instead, Bombardier added, the date of manufacture is
identified in an airplane's technical records such as a technical log
or technical logbook. Bombardier explained that the date in the
technical records is validated by a Bombardier Minister's Delegate-
Manufacturing (MDM), and that it believed this to be equivalent to the
date on the identification data plate. Bombardier stated that it
applied for and received a global alternative method of compliance
(AMOC) for AD 2021-10-02 that contains the requested change.
The FAA agrees. The date of manufacture found either on the
identification data plate of the airplane or in the airplane technical
logbook may be used to determine when inspections required in paragraph
(g) of this AD must be performed. The FAA has revised paragraph (g) of
this AD accordingly. The FAA has also revised paragraph (l) of this AD
to clarify that AMOCs approved previously for AD 2021-10-02 are
approved as AMOCs for the corresponding provisions of paragraph (g) of
this AD.
Conclusion
This product has been approved by the aviation authority of another
country and is approved for operation in the United States. Pursuant to
the FAA's bilateral agreement with this State of Design Authority, it
has notified the FAA of the unsafe condition described in the MCAI
referenced above. The FAA reviewed the relevant data, considered the
comments received, and determined that air safety requires adopting
this AD as proposed. Accordingly, the FAA is issuing this AD to address
the unsafe condition on this product. Except for minor editorial
changes, and any other changes described previously, this AD is adopted
as proposed in the NPRM. None of the changes will increase the economic
burden on any operator.
Material Incorporated by Reference Under 1 CFR Part 51
The FAA reviewed the following Bombardier temporary revisions:
<bullet> Bombardier Global Express, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-53, dated March 31, 2023 (for Model BD-
700-1A10 airplanes);
<bullet> Bombardier Global Express XRS, BD-700 Time Limits/
Maintenance Checks Temporary Revision 5-2-15, dated March 31, 2023 (for
Model BD-700-1A10 airplanes);
<bullet> Bombardier Global 6000, GL 6000 Time Limits/Maintenance
Checks Temporary Revision 5-2-20, dated March 31, 2023 (for Model BD-
700-1A10 airplanes);
<bullet> (Bombardier) Global 6500, GL 6500 Time Limits/Maintenance
Checks Temporary Revision 5-2-3, dated March 31, 2023 (for Model BD-
700-1A10 airplanes);
<bullet> Bombardier Global 5000, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-21, dated March 31, 2023 (for Model BD-
700-1A11 airplanes);
<bullet> Bombardier Global 5000, GL 5000 Featuring Global Vision
Flight Deck--Time Limits/Maintenance Checks Temporary Revision 5-2-20,
dated March 31, 2023 (for Model BD-700-1A11 airplanes); and
<bullet> (Bombardier) Global 5500, Time Limits/Maintenance Checks
GL 5500 Temporary Revision, 5-2-3, dated March 31, 2023 (for Model BD-
700-1A11 airplanes).
This material specifies an airworthiness limitation for a
certification maintenance requirement. These documents are distinct
since they
[[Page 8898]]
apply to different airplane models and configurations.
This AD also requires the following material, which the Director of
the Federal Register approved for incorporation by reference as of July
29, 2021 (86 FR 33088, June 24, 2021).
<bullet> Bombardier Service Bulletin 700-1A11-27-041, Revision 1,
dated December 7, 2020.
<bullet> Bombardier Service Bulletin 700-27-083, Revision 1, dated
December 7, 2020.
<bullet> Bombardier Service Bulletin 700-27-5012, Revision 1, dated
December 7, 2020.
<bullet> Bombardier Service Bulletin 700-27-5503, Revision 1, dated
December 7, 2020.
<bullet> Bombardier Service Bulletin 700-27-6012, Revision 1, dated
December 7, 2020.
<bullet> Bombardier Service Bulletin 700-27-6503, Revision 1, dated
December 7, 2020.
This material is reasonably available because the interested
parties have access to it through their normal course of business or by
the means identified in the ADDRESSES section.
Costs of Compliance
The FAA estimates that this AD affects 461 airplanes of U.S.
registry. The FAA estimates the following costs to comply with this AD:
The FAA has determined that revising the maintenance or inspection
program takes an average of 90 work-hours per operator, although the
agency recognizes that this number may vary from operator to operator.
Since operators incorporate maintenance or inspection program changes
for their affected fleet(s), the FAA has determined that a per-operator
estimate is more accurate than a per-airplane estimate. Therefore, the
agency estimates the average total cost per operator to be $7,650 (90
work-hours x $85 per work-hour).
The FAA estimates the total cost per operator for the new actions
to be $7,650 (90 work-hours x $85 per work-hour).
Estimated Costs for Required Actions
----------------------------------------------------------------------------------------------------------------
Action Labor cost Parts cost Cost per product Cost on U.S. operators
----------------------------------------------------------------------------------------------------------------
Retained actions from AD 2021- 22 work-hours x Up to $4 (for Up to $1,874.......... Up to $863,914.
10-02. $85 per hour = four cotter
$1,870. pins) *.
----------------------------------------------------------------------------------------------------------------
* Parts cost include replacement parts where necessary.
The FAA estimates the following costs to do any necessary on-
condition actions that would be required based on the results of any
required actions. The FAA has no way of determining the number of
aircraft that might need this on-condition action:
Estimated Costs of On-Condition Actions
------------------------------------------------------------------------
Labor cost Parts cost Cost per product
------------------------------------------------------------------------
5 work-hours x $85 per hour = $271 (for four $696
$425. bearings).
------------------------------------------------------------------------
The FAA has included all known costs in its cost estimate.
According to the manufacturer, however, some or all of the costs of
this AD may be covered under warranty, thereby reducing the cost impact
on affected operators.
Authority for This Rulemaking
Title 49 of the United States Code specifies the FAA's authority to
issue rules on aviation safety. Subtitle I, section 106, describes the
authority of the FAA Administrator. Subtitle VII: Aviation Programs,
describes in more detail the scope of the Agency's authority.
The FAA is issuing this rulemaking under the authority described in
Subtitle VII, Part A, Subpart III, Section 44701: General requirements.
Under that section, Congress charges the FAA with promoting safe flight
of civil aircraft in air commerce by prescribing regulations for
practices, methods, and procedures the Administrator finds necessary
for safety in air commerce. This regulation is within the scope of that
authority because it addresses an unsafe condition that is likely to
exist or develop on products identified in this rulemaking action.
Regulatory Findings
This AD will not have federalism implications under Executive Order
13132. This AD will not have a substantial direct effect on the States,
on the relationship between the national government and the States, or
on the distribution of power and responsibilities among the various
levels of government.
For the reasons discussed above, I certify that this AD:
(1) Is not a ``significant regulatory action'' under Executive
Order 12866,
(2) Will not affect intrastate aviation in Alaska, and
(3) Will not have a significant economic impact, positive or
negative, on a substantial number of small entities under the criteria
of the Regulatory Flexibility Act.
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by
reference, Safety.
The Amendment
Accordingly, under the authority delegated to me by the
Administrator, the FAA amends 14 CFR part 39 as follows:
PART 39--AIRWORTHINESS DIRECTIVES
0
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. 106(g), 40113, 44701.
Sec. 39.13 [Amended]
0
2. The FAA amends Sec. 39.13 by:
0
a. Removing Airworthiness Directive (AD) 2021-10-02, Amendment 39-21535
(86 FR 33088, June 24, 2021); and
0
b. Adding the following new AD:
2024-26-09 Bombardier, Inc.: Amendment 39-22924; Docket No. FAA-
2024-1483; Project Identifier MCAI-2023-01094-T.
(a) Effective Date
This airworthiness directive (AD) is effective March 11, 2025.
[[Page 8899]]
(b) Affected ADs
This AD replaces AD 2021-10-02, Amendment 39-21535 (86 FR 33088,
June 24, 2021) (AD 2021-10-02).
(c) Applicability
This AD applies to Bombardier, Inc., Model BD-700-1A10 and BD-
700-1A11 airplanes, certificated in any category, having serial
numbers 9002 through 60081 inclusive.
(d) Subject
Air Transport Association (ATA) of America Code 05, Time Limits/
Maintenance Checks; 27, Flight Controls.
(e) Reason
This AD was prompted by a determination that a new airworthiness
limitation is necessary. The FAA is issuing this AD to address sand
contamination and corrosion of the elevator torque tube bearings,
which could lead to binding or seizure of the bearings, and
potentially lead to a reduction in or loss of airplane pitch
control.
(f) Compliance
Comply with this AD within the compliance times specified,
unless already done.
(g) Retained Inspection and Corrective Actions, With Change
This paragraph restates the requirements of paragraph (g) of AD
2021-10-02, with a change to table 1 to paragraph (g), which
identifies the airplane marketing designation instead of the serial
number range, and a change to add an additional source for
identifying the date of airplane manufacture. Within 36 months from
July 29, 2021 (the effective date of AD 2021-10-02) or within 63
months from the date of airplane manufacture, as identified on the
identification data plate of the airplane or in the airplane
technical logbook, whichever occurs later: Do a general visual
inspection of the left- and right-hand elevator torque tube bearings
for any sand, dust, or corrosion; perform a functional test of the
elevator control system; and do all applicable corrective actions;
in accordance with the Accomplishment Instructions of paragraphs
2.B., 2.C., and 2.D. of the applicable material specified in table 1
to paragraph (g) of this AD. Applicable corrective actions must be
done before further flight. Repeat the general visual inspection and
functional test thereafter at intervals not to exceed 63 months.
Accomplishing the revision of the existing maintenance or inspection
program required by paragraph (i) of this AD terminates the
requirements of this paragraph.
Table 1 to Paragraph (g)--Service Information
[GRAPHIC] [TIFF OMITTED] TR04FE25.000
(h) No Reporting Requirement
Although the material identified in table 1 to paragraph (g) of
this AD specifies to submit certain information to the manufacturer,
this AD does not include that requirement.
(i) New Revision of the Existing Maintenance or Inspection Program
Within 30 days after the effective date of this AD, revise the
existing maintenance or inspection program, as applicable, to
incorporate the information specified in the applicable temporary
revision identified in table 2 to paragraph (i) of this AD. The
initial compliance time for doing the task is at the time specified
in the applicable temporary revision identified in table 2 to
paragraph (i) of this AD, or within 90 days after the effective date
of this AD, whichever occurs later. Accomplishing the revision of
the existing maintenance or inspection program required by this
paragraph terminates the actions required by paragraph (g) of this
AD.
[[Page 8900]]
Table 2 to Paragraph (i)--Applicable Temporary Revisions
[GRAPHIC] [TIFF OMITTED] TR04FE25.001
(j) New No Alternative Actions or Intervals
After the existing maintenance or inspection program has been
revised as required by paragraph (i) of this AD, no alternative
actions (e.g., inspections) or intervals may be used unless the
actions and intervals are approved as an alternative method of
compliance (AMOC) in accordance with the procedures specified in
paragraph (l)(1) of this AD.
(k) Credit for Previous Actions
(1) This paragraph provides credit for actions required by
paragraph (g) of this AD, if those actions were performed before
July 29, 2021 (the effective date of AD 2021-10-02) using the
applicable material specified in paragraphs (k)(1)(i) through (vi)
of this AD, which are not incorporated by reference in this AD.
(i) Bombardier Service Bulletin 700-1A11-27-041, dated July 23,
2020.
(ii) Bombardier Service Bulletin 700-27-083, dated July 23,
2020.
(iii) Bombardier Service Bulletin 700-27-5012, dated July 23,
2020.
(iv) Bombardier Service Bulletin 700-27-5503, dated July 23,
2020.
(v) Bombardier Service Bulletin 700-27-6012, dated July 23,
2020.
(vi) Bombardier Service Bulletin 700-27-6503, dated July 23,
2020.
(2) This paragraph provides credit for the initial and
repetitive inspection actions required by paragraph (i) of this AD
if those actions were performed before the effective date of this AD
using the applicable material identified in table 1 to paragraph (g)
of this AD, which were incorporated by reference in AD 2021-10-02.
(l) Additional AD Provisions
The following provisions also apply to this AD:
(1) Alternative Methods of Compliance (AMOCs): The Manager,
International Validation Branch, FAA, has the authority to approve
AMOCs for this AD, if requested using the procedures found in 14 CFR
39.19. In accordance with 14 CFR 39.19, send your request to your
principal inspector or responsible Flight Standards Office, as
appropriate. If sending information directly to the manager of the
International Validation Branch, mail it to the address identified
in paragraph (m)(1) of this AD. Information may be emailed to:
[email protected].
(i) Before using any approved AMOC, notify your appropriate
principal inspector, or lacking a principal inspector, the manager
of the responsible Flight Standards Office.
(ii) AMOCs approved previously for AD 2021-10-02, are approved
as AMOCs for the corresponding provisions of paragraph (g) of this
AD.
(2) Contacting the Manufacturer: For any requirement in this AD
to obtain instructions from a manufacturer, the instructions must be
accomplished using a method approved by the Manager, International
Validation Branch, FAA; or Transport Canada; or Bombardier, Inc.'s
Transport Canada Design Approval Organization (DAO). If approved by
the DAO, the approval must include the DAO-authorized signature.
(m) Additional Information
(1) For more information about this AD, contact Gabriel Kim,
Aviation Safety Engineer, FAA, 1600 Stewart Avenue, Suite 410,
Westbury, NY 11590; telephone 516-228-7300; email [email protected].
(2) Material identified in this AD that is not incorporated by
reference is available at the address specified in paragraph (n)(5)
of this AD.
(n) Material Incorporated by Reference
(1) The Director of the Federal Register approved the
incorporation by reference (IBR) of the material listed in this
paragraph under 5 U.S.C. 552(a) and 1 CFR part 51.
(2) You must use this material as applicable to do the actions
required by this AD, unless this AD specifies otherwise.
(3) The following material was approved for IBR on March 11,
2025.
(i) (Bombardier) Global 5500, GL 5500 Time Limits/Maintenance
Checks Temporary Revision, 5-2-3, dated March 31, 2023.
(ii) (Bombardier) Global 6500, GL 6500 Time Limits/Maintenance
Checks Temporary Revision 5-2-3, dated March 31, 2023.
(iii) Bombardier Global 5000, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-21, dated March 31, 2023.
(iv) Bombardier Global 5000, GL 5000 Featuring Global Vision
Flight Deck Time Limits/Maintenance Checks Temporary Revision 5-2-
20, dated March 31, 2023.
(v) Bombardier Global 6000, GL 6000 Time Limits/Maintenance
Checks Temporary Revision 5-2-20, dated March 31, 2023.
[[Page 8901]]
(vi) Bombardier Global Express, BD-700 Time Limits/Maintenance
Checks Temporary Revision 5-2-53, dated March 31, 2023.
(vii) Bombardier Global Express XRS, BD-700 Time Limits/
Maintenance Checks Temporary Revision 5-2-15, dated March 31, 2023.
(4) The following material was approved for IBR on July 29, 2021
(86 FR 33088, June 24, 2021).
(i) Bombardier Service Bulletin 700-1A11-27-041, Revision 1,
dated December 7, 2020.
(ii) Bombardier Service Bulletin 700-27-083, Revision 1, dated
December 7, 2020.
(iii) Bombardier Service Bulletin 700-27-5012, Revision 1, dated
December 7, 2020.
(iv) Bombardier Service Bulletin 700-27-5503, Revision 1, dated
December 7, 2020.
(v) Bombardier Service Bulletin 700-27-6012, Revision 1, dated
December 7, 2020.
(vi) Bombardier Service Bulletin 700-27-6503, Revision 1, dated
December 7, 2020.
(5) For Bombardier material identified in this AD, contact
Bombardier Business Aircraft Customer Response Center, 400
C[ocirc]te-Vertu Road West, Dorval, Qu[eacute]bec H4S 1Y9, Canada;
telephone 514-855-2999; email bombardier.com">ac.yul@aero.bombardier.com; website
bombardier.com.
(6) You may view this material at the FAA, Airworthiness
Products Section, Operational Safety Branch, 2200 South 216th St.,
Des Moines, WA. For information on the availability of this material
at the FAA, call 206-231-3195.
(7) You may view this material at the National Archives and
Records Administration (NARA). For information on the availability
of this material at NARA, visit www.archives.gov/federal-register/cfr/ibr-locations or email [email protected].
Issued on December 30, 2024.
Steven W. Thompson,
Acting Deputy Director, Compliance & Airworthiness Division, Aircraft
Certification Service.
[FR Doc. 2025-02147 Filed 2-3-25; 8:45 am]
BILLING CODE 4910-13-P
Why this text is shown
The complete text was extracted from the official GovInfo HTML edition for this publication. Acquired 2026-10-09T01:26:11.597096+00:00. Text extraction preserves the recorded source wording; it does not determine current requirements.
Open the captured official edition
- Source SHA-256
- 378b5a30d127bf319fdbf7cf77ce3c0e59f377c80c1287ee63b6f37190ccee2c
- Text SHA-256
- 42b77dd57973e73286d34f154b19847998b50bbc8f758baa8d44169b16bb6f03
Return to the full metadata catalog · Search complete publication text · Explore retained publication text and evidence
Coverage and limits
These are dated publication metadata, recorded clauses and literal source observations. Word, model-label, header and reference matches do not establish current legal effect, manufacturer/model identity, aircraft applicability, installed configuration or compliance.
The collection uses 33 explicit annual source snapshots. Source captures and operative-text qualifications have separate states. Missing information remains unknown.