Published 2009-11-12 · Federal Register document E9-26622
Airworthiness Directives; Empresa Brasileira de Aeronáutica S.A. (EMBRAER) Model ERJ 170 and ERJ 190 Airplanes
Publication summary
We are superseding an existing airworthiness directive (AD) for the products listed above. This AD results from mandatory continuing airworthiness information (MCAI) originated by an aviation authority of another country to identify and correct an unsafe condition on an aviation product. The MCAI describes the unsafe condition as:
Why this record is shown
Source: Federal Register annual FAA metadata. Acquired 2026-09-03T22:23:30.011257+00:00. The title, summary and date are source facts.
- Source revision
- federal_register_ad_metadata_2009-cb57e588bd107238
- Source row
- results[314]
- Raw source SHA-256
- cb57e588bd10723805ef0ea28ddc0685de14711012023c7e7d12178879efaeed
Final-rule publication
Recorded publication clauses
- AD identifier printed in this edition
- 2009-23-08
- Effective date printed in this edition
- 2009-12-17
Read 14 complete recorded clauses
Effective Date
Effective Date
(a) This airworthiness directive (AD) becomes effective December
17, 2009.
Exact source excerpt. Text positions 8982–9079, end exclusive, in the original decoded publication. SHA-256: 3099037ddab9a0c574185db25ffd11d6b680a68009587e9521d5f877975b0b96
Affected ADs
Affected ADs
(b) This AD supersedes AD 2007-06-53, Amendment 39-15035.
Exact source excerpt. Text positions 9079–9156, end exclusive, in the original decoded publication. SHA-256: bc1db50d6c5e4be66b1354d529d1b655e618dce9030662e0ede5ea2dc9072c74
Applicability wording · Applicability
Applicability
(c) This AD applies to EMBRAER Model ERJ 170-100 LR, -100 STD, -
100 SE, -100 SU, -200 LR, -200 STD, and -200 SU airplanes; and ERJ
190-100 STD, -100 LR, -100 IGW, -200 LR, -200 STD, and -200 IGW
airplanes; certificated in any category.
Exact source excerpt. Text positions 9156–9415, end exclusive, in the original decoded publication. SHA-256: ab4b6055da567a612f4360b34e5c9dbef4a49901f6550af643fd5da6c89314c0
Subject
Subject
(d) Air Transport Association (ATA) of America Code 52: Doors.
Exact source excerpt. Text positions 9415–9492, end exclusive, in the original decoded publication. SHA-256: de8d001e96909c87344f451cabaec69867c231ac181df4883b2198a61d3afeeb
Reason
Reason
(e) The mandatory continuing airworthiness information (MCAI)
states:
It has been found the occurrence of two events of aircraft being
dispatched with the cargo door opened without indication. In one of
the events the aircraft took off with the cargo door opened.
The unsafe condition is a cargo door opening during flight,
which could result in reduced structural integrity and consequent
rapid decompression of the airplane. Required actions include
repetitive inspections of the forward and aft cargo doors to detect
signs of interference between the lock handle and the aft edge liner
assembly and reworking the assembly; a one-time inspection for signs
of damage of the lateral roller fitting on the forward and aft
[[Page 58193]]
cargo door frames at the fuselage and replacement of the roller if
necessary, and modification of the cargo door, which ends the
repetitive inspections. After accomplishing the modification, the
actions include incorporating information into the maintenance
program to include the operational (OPC) and functional (FNC) checks
of the forward and aft cargo doors and accomplishing repetitive OPC
and FNC checks.
Exact source excerpt. Text positions 9492–10679, end exclusive, in the original decoded publication. SHA-256: 9ba70ea71cc434e4dd3cd2458560b3c17f59f42473c7d57e63ef92addca6c82a
Compliance
Compliance
(f) Required as indicated, unless accomplished previously.
Restatement of Requirements of AD 2007-06-53, With New Service
Information
Exact source excerpt. Text positions 10679–10832, end exclusive, in the original decoded publication. SHA-256: fe0183c35d8c701c67e6d5ccac66f58fc734390310a0f1d25ebbfc5645475cbd
Preflight Verification of Correct Door Closure
Preflight Verification of Correct Door Closure
(g) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: As of 24 hours after May 7, 2007 (the
effective date of AD 2007-06-53), before each flight after closing
the cargo doors, verify that the forward and aft cargo doors are
closed flush with the fuselage skin, and that all 4 latched and
locked indicators at the bottom of each door are green. Persons
qualified to do this verification are mechanics and flightcrew
members. If it cannot be verified that both doors are closed flush
with the fuselage skin, and that all 4 latched and locked indicators
at the bottom of each door are green, repair before further flight.
Repeat the verification before every flight until accomplishment of
the actions required by paragraph (h) of this AD.
Exact source excerpt. Text positions 10832–11734, end exclusive, in the original decoded publication. SHA-256: 5ebb5d919d1000a3adc5e0392cbf4249691d3d54a116c17a58ca22a567ec73a7
Inspection for Interference and Damage
Inspection for Interference and Damage
(h) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: Within 10 days after May 7, 2007, do the
actions specified in paragraphs (h)(1), (h)(2), and (h)(3) of this
AD, in accordance with the Accomplishment Instructions of Embraer
Alert Service Bulletin 170-52-A036 (for Model ERJ 170 airplanes) or
190-52-A018 (for Model ERJ 190 airplanes), both dated March 12,
2007; or Revision 01, both dated March 23, 2007; as applicable. As
of the effective date of this AD, use Revision 01 of Embraer Alert
Service Bulletin 170-52-A036 or 190-52-A018.
(1) Remove the roller fitting cover plate on the forward and aft
cargo door frames.
(2) Perform a detailed inspection of the forward and aft cargo
doors to detect signs of interference between the lock handle and
the aft edge liner assembly. Then rework the aft edge liner assembly
at the applicable time specified in paragraph (h)(2)(i) or
(h)(2)(ii) of this AD.
(i) If any sign of interference is detected: Rework the assembly
before further flight.
(ii) If no sign of interference is detected: Rework the assembly
within 150 flight cycles after the inspection.
(3) Perform a detailed inspection for signs of damage of the
lateral roller fitting on the forward and aft cargo door frames at
the fuselage. If any damage is found, replace the lateral roller
fitting before further flight with a new roller fitting having the
same part number, in accordance with Embraer Alert Service Bulletin
170-52-A036 or 190-52-A018, as applicable.
(4) Actions done before May 7, 2007, in accordance with Embraer
Alert Service Bulletin 170-52-A036 or 190-52-A018, both dated March
12, 2007, are acceptable for compliance with the corresponding
requirements of this AD.
Note 1: For the purposes of this AD, a detailed inspection is:
``An intensive examination of a specific item, installation, or
assembly to detect damage, failure, or irregularity. Available
lighting is normally supplemented with a direct source of good
lighting at an intensity deemed appropriate. Inspection aids such as
mirror, magnifying lenses, etc., may be necessary. Surface cleaning
and elaborate procedures may be required.''
Note 2: Embraer Alert Service Bulletins 170-52-A036 and 190-52-
A018 refer to Embraer Service Bulletins 170-50-0006 and 190-50-0006,
respectively, as additional sources of guidance for the rework and
roller fitting cover plate removal. Embraer Alert Service Bulletins
170-50-0006 and 190-50-0006 are currently at Revision 01, dated
March 13, 2007.
Exact source excerpt. Text positions 11734–14424, end exclusive, in the original decoded publication. SHA-256: 4ab0b0fc114294efe52b8c008170ebc5ce87ad0449b42008f0b540b285669408
Repetitive Inspections for Damage
Repetitive Inspections for Damage
(i) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: Repeat the inspection specified in paragraph
(h)(3) of this AD at intervals not to exceed 150 flight cycles until
the terminating action specified in paragraph (k)(3) of this AD has
been accomplished.
Exact source excerpt. Text positions 14424–14824, end exclusive, in the original decoded publication. SHA-256: 9e640d9c18139dc48a70a23b69ce7a0aed391ed27a1388df78dfb729ea57ad45
Parts Installation
Parts Installation
(j) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: As of May 7, 2007, no person may install a
roller fitting cover plate on the forward and aft cargo door frames
on any airplane.
New Requirements of This AD
Exact source excerpt. Text positions 14824–15164, end exclusive, in the original decoded publication. SHA-256: 01b644c9b9adc293edc0568160bfd4036e72ffc5cdac02f3dafb9dd39d43b388
Actions and Compliance
Actions and Compliance
(k) Unless already done, do the following actions.
(1) For Model ERJ 190-200 LR, -200 STD, and -200 IGW airplanes:
As of 24 hours after the effective date of this AD, before each
flight after closing the cargo doors, verify that the forward and
aft cargo doors are closed flush with the fuselage skin, and that
all 4 latched and locked indicators at the bottom of each door are
green. Persons qualified to do this verification are mechanics and
flightcrew members. If it cannot be verified that both doors are
closed flush with the fuselage skin, and that all 4 latched and
locked indicators at the bottom of each door are green, repair
before further flight. Repeat the verification before every flight
until accomplishment of the actions required by paragraph (k)(2) of
this AD.
(2) For Model ERJ 190-200 LR, -200 STD, and -200 IGW airplanes:
Within 10 days after the effective date of this AD, do the actions
specified in paragraphs (k)(2)(i), (k)(2)(ii), and (k)(2)(iii) of
this AD, in accordance with the Accomplishment Instructions of
Embraer Alert Service Bulletin 190-52-A018, Revision 01, dated March
23, 2007. Repeat the inspection specified in paragraph (k)(2)(iii)
of this AD at intervals not to exceed 150 flight cycles until the
terminating action specified in paragraph (k)(3) of this AD has been
accomplished.
(i) Remove the roller fitting cover plate on the forward and aft
cargo door frames.
(ii) Perform a detailed inspection of the forward and aft cargo
doors to detect signs of interference between the lock handle and
the aft edge liner assembly. Then rework the aft edge liner assembly
at the applicable time specified in paragraph (k)(2)(ii)(A) or
(k)(2)(ii)(B) of this AD.
(A) If any sign of interference is detected: Rework the assembly
before further flight.
(B) If no sign of interference is detected: Rework the assembly
within 150 flight cycles after the inspection.
(iii) Perform a detailed inspection for signs of damage of the
lateral roller fitting on the forward and aft cargo door frames at
the fuselage. If any damage is found, replace the lateral roller
fitting before further flight with a new roller fitting having the
same part number, in accordance with Embraer Alert Service Bulletin
190-52-A018, Revision 01, dated March 23, 2007.
(3) For all airplanes: Within 5,000 flight cycles after the
effective date of this AD, do the actions specified in paragraphs
(k)(3)(i) and (k)(3)(ii) of this AD on the forward and aft cargo
doors. Accomplishing the actions in this paragraph terminates the
repetitive inspections required by paragraphs (i) and (k)(2) of this
AD.
(i) Relocate the cargo door closed indication sensor in
accordance with the Accomplishment Instructions of Embraer Service
Bulletin 170-52-0041, Revision 01, dated June 13, 2008; or 190-52-
0023, Revision 02, dated March 11, 2008; as applicable.
(ii) Modify the cargo door lock handle mechanism and replace the
forward and aft cargo door roller fittings having part number (P/N)
170-92569-401 and 170-85452-401 with new fittings having P/N 170-
92569-403 and 170-85452-403, as applicable. Do the modification in
accordance with the Accomplishment Instructions of Embraer Service
Bulletins 170-52-0044, dated January 18, 2008; or 190-52-0027, dated
March 20, 2008; as applicable.
(4) Actions done before the effective date of this AD in
accordance with Embraer Service Bulletin 170-52-0041, dated
September 6, 2007; or 190-52-0023, dated September 6, 2007, or
Revision 01, dated December 6, 2007; as applicable; are acceptable
for compliance with the corresponding requirements of this AD.
(5) Within 12 months after the effective date of this AD or 12
months after accomplishing the modification required by paragraph
(k)(3) of this AD, whichever occurs later: Incorporate information
into the maintenance program to include the operational (OPC) and
functional (FNC) checks of the forward and aft cargo doors; in
accordance with a method approved by the
[[Page 58194]]
Manager, International Branch, ANM-116, Transport Airplane
Directorate, FAA; or the Ag[ecirc]ncia Nacional de
Avia[ccedil][atilde]o Civil (or its delegated agent). Within 6,000
flight hours after doing the actions required by paragraph (k)(3) of
this AD, do the OPC and FNC checks and repeat the checks thereafter
at intervals not to exceed 6,000 flight hours.
Note 3: Guidance on the OPC and FNC checks specified in
paragraph (k)(5) of this AD can be found in the document specified
in Table 1 of this AD, as applicable:
Table 1--OPC and FNC Guidance
------------------------------------------------------------------------
Manual-- Task-- Date--
------------------------------------------------------------------------
Embraer 170 Aircraft 52-31-00-710-801-A/ July 15, 2008.
Maintenance Manual. 500.
52-31-20-720-801-A/ July 15, 2008.
500.
52-32-00-710-801-A/ July 15, 2008.
500.
52-32-20-720-801-A/ July 15, 2008.
500.
Embraer 190 Aircraft 52-31-00-710-801-A/ July 15, 2008.
Maintenance Manual. 500.
52-31-20-720-801-A/ July 15, 2008.
500.
52-32-00-710-801-A/ July 15, 2008.
500.
52-32-20-720-801-A/ July 15, 2008.
500.
------------------------------------------------------------------------
Note 4: For the purposes of this AD, a functional check (FNC)
is: ``A quantitative check to determine if one or more functions of
an item perform within specified limits.''
Note 5: For the purposes of this AD, an operational check (OPC)
is: ``A task to determine if an item is fulfilling its intended
purpose. Since it is a failure finding task, it does not require
quantitative tolerances.''
FAA AD Differences
Note 6: This AD differs from the MCAI and/or service
information as follows: Where the MCAI includes a compliance time of
``after accomplishment of the modification'' for revising the
maintenance program for Model ERJ-170 airplanes, we have determined
that a compliance time of ``within 12 months after the effective
date of the AD or within 12 months after accomplishment of the
modification, whichever occurs later'' is appropriate. This
compliance time is equivalent to the compliance time required for
Model ERJ-190 airplanes. The manufacturer and ANAC agree with this
compliance time.
Exact source excerpt. Text positions 15164–22036, end exclusive, in the original decoded publication. SHA-256: 801bfad7ee48f2f5187c2b302754d15a3608df847dbce03391866dbd8bbed10a
Other FAA AD Provisions
Other FAA AD Provisions
(l) The following provisions also apply to this AD:
(1) Alternative Methods of Compliance (AMOCs): The Manager,
International Branch, FAA, has the authority to approve AMOCs for
this AD, if requested using the procedures found in 14 CFR 39.19.
Send information to ATTN: Kenny Kaulia, Aerospace Engineer,
International Branch, ANM-116, FAA, Transport Airplane Directorate,
1601 Lind Avenue, SW., Renton, Washington 98055-4056; telephone
(425) 227-2848; fax (425) 227-1149. Before using any approved AMOC
on any airplane to which the AMOC applies, notify your principal
maintenance inspector (PMI) or principal avionics inspector (PAI),
as appropriate, or lacking a principal inspector, your local Flight
Standards District Office. The AMOC approval letter must
specifically reference this AD. AMOCs approved previously in
accordance with AD 2007-06-53, are approved as AMOCs for the
corresponding provisions of paragraph (i) of this AD.
(2) Airworthy Product: For any requirement in this AD to obtain
corrective actions from a manufacturer or other source, use these
actions if they are FAA-approved. Corrective actions are considered
FAA-approved if they are approved by the State of Design Authority
(or their delegated agent). You are required to assure the product
is airworthy before it is returned to service.
(3) Reporting Requirements: For any reporting requirement in
this AD, under the provisions of the Paperwork Reduction Act (44
U.S.C. 3501 et seq.), the Office of Management and Budget (OMB) has
approved the information collection requirements and has assigned
OMB Control Number 2120-0056.
Exact source excerpt. Text positions 22036–23705, end exclusive, in the original decoded publication. SHA-256: be4ec4c1f37d9eeb25e310af0c3904ff2ca76a22bada83807d638ae5d8ef739b
Related Information
Related Information
(m) Refer to Brazilian Airworthiness Directives 2007-03-01R1,
dated June 9, 2008, and 2007-03-02R2, dated November 21, 2008; and
the service information contained in Table 2 of this AD; for related
information.
Table 2--Service Information
------------------------------------------------------------------------
Service bulletin Revision Date
------------------------------------------------------------------------
Embraer Alert Service Bulletin 170- 01 March 23, 2007.
52-A036.
Embraer Alert Service Bulletin 190- 01 March 23, 2007.
52-A018.
Embraer Service Bulletin 01 June 13, 2008.
170[dash]52[dash]0041.
Embraer Service Bulletin \1\ January 18, 2008.
170[dash]52[dash]0044.
Embraer Service Bulletin 02 March 11, 2008.
190[dash]52[dash]0023.
Embraer Service Bulletin \1\ March 20, 2008.
190[dash]52[dash]0027.
------------------------------------------------------------------------
\1\ Original.
Exact source excerpt. Text positions 23705–24788, end exclusive, in the original decoded publication. SHA-256: 3e56321789e4619b5a661c252749bf81cd0fc1ab45a7b9583fb4529e2180553d
Material Incorporated by Reference
Material Incorporated by Reference
(n) You must use the applicable service information contained in
Table 3 of this AD to do the actions required by this AD, unless the
AD specifies otherwise.
Table 3--Material Incorporated by Reference
------------------------------------------------------------------------
Service bulletin Revision Date
------------------------------------------------------------------------
Embraer Alert Service Bulletin 170- 01 March 23, 2007.
52-A036.
Embraer Alert Service Bulletin 190- 01 March 23, 2007.
52-A018.
Embraer Service Bulletin 170-52- 01 June 13, 2008.
0041.
Embraer Service Bulletin 170-52- \1\ January 18, 2008.
0044.
Embraer Service Bulletin 190-52- 02 March 11, 2008.
0023.
[[Page 58195]]
Embraer Service Bulletin 190-52- \1\ March 20, 2008.
0027.
------------------------------------------------------------------------
\1\ Original.
(1) For service information identified in this AD, contact
Empresa Brasileira de Aeronautica S.A. (EMBRAER), Technical
Publications Section (PC 060), Av. Brigadeiro Faria Lima, 2170--
Putim--12227-901 S[atilde]o Jose dos Campos--SP--Brasil; telephone:
+55 12 3927-5852 or +55 12 3309-0732; fax: +55 12 3927-7546; e-mail:
[email protected]; Internet: http://www.flyembraer.com.
(2) You may review copies of the service information at the FAA,
Transport Airplane Directorate, 1601 Lind Avenue SW., Renton,
Washington. For information on the availability of this material at
the FAA, call 425-227-1221 or 425-227-1152.
(3) You may also review copies of the service information that
is incorporated by reference at the National Archives and Records
Administration (NARA). For information on the availability of this
material at NARA, call 202-741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
Exact source excerpt. Text positions 24788–26762, end exclusive, in the original decoded publication. SHA-256: 3ef2ea3414ec675eaca2602fb8389c8d92dd4213ea04ecf86c9b07ba4a1545b4
No replacement link has been established from this edition. The complete historical rule chain and current legal effect remain unknown.
Find all recorded historical references to AD 2009-23-08 · 0 printed reference observations in this pinned collection.
These are observations from one dated publication. Current legal status is unknown; aircraft applicability, installed configuration, compliance and burden require separate evidence. Missing or unparsed conditions remain unknown.
Why these observations are shown
They were extracted offline from the same immutable official HTML source as the complete recorded text. The dated source wording, original text coordinates and exact quote digests are retained. PDF/text agreement and current regulatory effect have not been qualified.
Observation revision: whole-ad-publication-clause-observations-1.0.1. Text SHA-256: 9f8a65a72c4685aa488b3421409a6449c33fc8d31e7e6e98238764babf5a1ac8. Source manifest: 440d12aaa24e4cae1711b01beb14acc6d427730947c2dbfd1d922fa6ad0e4599.
Official source · 2009-11-12
Publication text
This is the complete recorded text of this dated publication.
Current legal effect is unknown. Aircraft applicability, installed configuration and compliance require separate evidence. PDF/text agreement has not been evaluated.
Read the complete official publication text
[Federal Register Volume 74, Number 217 (Thursday, November 12, 2009)]
[Rules and Regulations]
[Pages 58191-58195]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E9-26622]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
14 CFR Part 39
[Docket No. FAA-2009-0687; Directorate Identifier 2009-NM-033-AD;
Amendment 39-16080; AD 2009-23-08]
RIN 2120-AA64
Airworthiness Directives; Empresa Brasileira de
Aeron[aacute]utica S.A. (EMBRAER) Model ERJ 170 and ERJ 190 Airplanes
AGENCY: Federal Aviation Administration (FAA), Department of
Transportation (DOT).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: We are superseding an existing airworthiness directive (AD)
for the products listed above. This AD results from mandatory
continuing airworthiness information (MCAI) originated by an aviation
authority of another country to identify and correct an unsafe
condition on an aviation product. The MCAI describes the unsafe
condition as:
It has been found the occurrence of two events of aircraft being
dispatched with the cargo door opened without indication. In one of
the events the aircraft took off with the cargo door opened.
* * * * *
The unsafe condition is a cargo door opening during flight, which
could result in reduced structural integrity and consequent rapid
decompression of the airplane. We are issuing this AD to require
actions to correct the unsafe condition on these products.
DATES: This AD becomes effective December 17, 2009.
The Director of the Federal Register approved the incorporation by
reference of certain publications listed in this AD as of December 17,
2009.
ADDRESSES: You may examine the AD docket on the Internet at http://www.regulations.gov or in person at the U.S. Department of
Transportation, Docket Operations, M-30, West Building Ground Floor,
Room W12-140, 1200 New Jersey Avenue SE., Washington, DC.
FOR FURTHER INFORMATION CONTACT: Kenny Kaulia, Aerospace Engineer,
International Branch, ANM-116, FAA, Transport Airplane Directorate,
1601 Lind Avenue SW., Renton, Washington 98057-3356; telephone (425)
227-2848; fax (425) 227-1149.
SUPPLEMENTARY INFORMATION:
Discussion
We issued a notice of proposed rulemaking (NPRM) to amend 14 CFR
part 39 to include an AD that would apply to the specified products.
That NPRM was published in the Federal Register on August 18, 2009 (74
FR 41642), and proposed to supersede AD 2007-06-53, Amendment 39-15035
(72 FR 21088, April 30, 2007). That NPRM proposed to correct an unsafe
condition for the specified products. The MCAI states:
It has been found the occurrence of two events of aircraft being
dispatched with the cargo door opened without indication. In one of
the events the aircraft took off with the cargo door opened.
The unsafe condition is a cargo door opening during flight, which
could result in reduced structural integrity and consequent rapid
decompression of the airplane. Required actions include repetitive
inspections of the forward and aft cargo doors to detect signs of
interference between the lock handle and the aft edge liner assembly
and
[[Page 58192]]
reworking the assembly; a one-time inspection for signs of damage of
the lateral roller fitting on the forward and aft cargo door frames at
the fuselage and replacement of the roller if necessary, and
modification of the cargo door, which ends the repetitive inspections.
After accomplishing the modification, the actions include incorporating
information into the maintenance program to include the operational
(OPC) and functional (FNC) checks of the forward and aft cargo doors
and accomplishing repetitive OPC and FNC checks. You may obtain further
information by examining the MCAI in the AD docket.
Comments
We gave the public the opportunity to participate in developing
this AD. We received no comments on the NPRM or on the determination of
the cost to the public.
Conclusion
We reviewed the available data and determined that air safety and
the public interest require adopting the AD as proposed.
Differences Between This AD and the MCAI or Service Information
We have reviewed the MCAI and related service information and, in
general, agree with their substance. But we might have found it
necessary to use different words from those in the MCAI to ensure the
AD is clear for U.S. operators and is enforceable. In making these
changes, we do not intend to differ substantively from the information
provided in the MCAI and related service information.
We might also have required different actions in this AD from those
in the MCAI in order to follow our FAA policies. Any such differences
are highlighted in a Note within the AD.
Costs of Compliance
We estimate that this AD will affect about 145 products of U.S.
registry.
The actions that are required by AD 2007-06-53 and retained in this
AD take about 1 work-hour per product, at an average labor rate of $80
per work hour. Based on these figures, the estimated cost of the
currently required actions is $80 per product.
We estimate that it would take about 7 work-hours per product to
comply with the new basic requirements of this AD. The average labor
rate is $80 per work-hour. Required parts will cost about $17,162 per
product. Where the service information lists required parts costs that
are covered under warranty, we have assumed that there will be no
charge for these costs. As we do not control warranty coverage for
affected parties, some parties may incur costs higher than estimated
here. Based on these figures, we estimate the cost of the AD on U.S.
operators to be $2,569,690, or $17,722 per product.
Authority for This Rulemaking
Title 49 of the United States Code specifies the FAA's authority to
issue rules on aviation safety. Subtitle I, section 106, describes the
authority of the FAA Administrator. ``Subtitle VII: Aviation
Programs,'' describes in more detail the scope of the Agency's
authority.
We are issuing this rulemaking under the authority described in
``Subtitle VII, Part A, Subpart III, Section 44701: General
requirements.'' Under that section, Congress charges the FAA with
promoting safe flight of civil aircraft in air commerce by prescribing
regulations for practices, methods, and procedures the Administrator
finds necessary for safety in air commerce. This regulation is within
the scope of that authority because it addresses an unsafe condition
that is likely to exist or develop on products identified in this
rulemaking action.
Regulatory Findings
We determined that this AD will not have federalism implications
under Executive Order 13132. This AD will not have a substantial direct
effect on the States, on the relationship between the national
government and the States, or on the distribution of power and
responsibilities among the various levels of government.
For the reasons discussed above, I certify this AD:
1. Is not a ``significant regulatory action'' under Executive Order
12866;
2. Is not a ``significant rule'' under the DOT Regulatory Policies
and Procedures (44 FR 11034, February 26, 1979); and
3. Will not have a significant economic impact, positive or
negative, on a substantial number of small entities under the criteria
of the Regulatory Flexibility Act.
We prepared a regulatory evaluation of the estimated costs to
comply with this AD and placed it in the AD docket.
Examining the AD Docket
You may examine the AD docket on the Internet at http://www.regulations.gov; or in person at the Docket Operations office
between 9 a.m. and 5 p.m., Monday through Friday, except Federal
holidays. The AD docket contains the NPRM, the regulatory evaluation,
any comments received, and other information. The street address for
the Docket Operations office (telephone (800) 647-5527) is in the
ADDRESSES section. Comments will be available in the AD docket shortly
after receipt.
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by
reference, Safety.
Adoption of the Amendment
0
Accordingly, under the authority delegated to me by the Administrator,
the FAA amends 14 CFR part 39 as follows:
PART 39--AIRWORTHINESS DIRECTIVES
0
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. 106(g), 40113, 44701.
Sec. 39.13 [Amended]
0
2. The FAA amends Sec. 39.13 by removing Amendment 39-15035 (72 FR
21088, April 30, 2007) and adding the following new AD:
2009-23-08 Empresa Brasileira de Aeron[aacute]utica S.A. (EMBRAER):
Amendment 39-16080. Docket No. FAA-2009-0687; Directorate Identifier
2009-NM-033-AD.
Effective Date
(a) This airworthiness directive (AD) becomes effective December
17, 2009.
Affected ADs
(b) This AD supersedes AD 2007-06-53, Amendment 39-15035.
Applicability
(c) This AD applies to EMBRAER Model ERJ 170-100 LR, -100 STD, -
100 SE, -100 SU, -200 LR, -200 STD, and -200 SU airplanes; and ERJ
190-100 STD, -100 LR, -100 IGW, -200 LR, -200 STD, and -200 IGW
airplanes; certificated in any category.
Subject
(d) Air Transport Association (ATA) of America Code 52: Doors.
Reason
(e) The mandatory continuing airworthiness information (MCAI)
states:
It has been found the occurrence of two events of aircraft being
dispatched with the cargo door opened without indication. In one of
the events the aircraft took off with the cargo door opened.
The unsafe condition is a cargo door opening during flight,
which could result in reduced structural integrity and consequent
rapid decompression of the airplane. Required actions include
repetitive inspections of the forward and aft cargo doors to detect
signs of interference between the lock handle and the aft edge liner
assembly and reworking the assembly; a one-time inspection for signs
of damage of the lateral roller fitting on the forward and aft
[[Page 58193]]
cargo door frames at the fuselage and replacement of the roller if
necessary, and modification of the cargo door, which ends the
repetitive inspections. After accomplishing the modification, the
actions include incorporating information into the maintenance
program to include the operational (OPC) and functional (FNC) checks
of the forward and aft cargo doors and accomplishing repetitive OPC
and FNC checks.
Compliance
(f) Required as indicated, unless accomplished previously.
Restatement of Requirements of AD 2007-06-53, With New Service
Information
Preflight Verification of Correct Door Closure
(g) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: As of 24 hours after May 7, 2007 (the
effective date of AD 2007-06-53), before each flight after closing
the cargo doors, verify that the forward and aft cargo doors are
closed flush with the fuselage skin, and that all 4 latched and
locked indicators at the bottom of each door are green. Persons
qualified to do this verification are mechanics and flightcrew
members. If it cannot be verified that both doors are closed flush
with the fuselage skin, and that all 4 latched and locked indicators
at the bottom of each door are green, repair before further flight.
Repeat the verification before every flight until accomplishment of
the actions required by paragraph (h) of this AD.
Inspection for Interference and Damage
(h) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: Within 10 days after May 7, 2007, do the
actions specified in paragraphs (h)(1), (h)(2), and (h)(3) of this
AD, in accordance with the Accomplishment Instructions of Embraer
Alert Service Bulletin 170-52-A036 (for Model ERJ 170 airplanes) or
190-52-A018 (for Model ERJ 190 airplanes), both dated March 12,
2007; or Revision 01, both dated March 23, 2007; as applicable. As
of the effective date of this AD, use Revision 01 of Embraer Alert
Service Bulletin 170-52-A036 or 190-52-A018.
(1) Remove the roller fitting cover plate on the forward and aft
cargo door frames.
(2) Perform a detailed inspection of the forward and aft cargo
doors to detect signs of interference between the lock handle and
the aft edge liner assembly. Then rework the aft edge liner assembly
at the applicable time specified in paragraph (h)(2)(i) or
(h)(2)(ii) of this AD.
(i) If any sign of interference is detected: Rework the assembly
before further flight.
(ii) If no sign of interference is detected: Rework the assembly
within 150 flight cycles after the inspection.
(3) Perform a detailed inspection for signs of damage of the
lateral roller fitting on the forward and aft cargo door frames at
the fuselage. If any damage is found, replace the lateral roller
fitting before further flight with a new roller fitting having the
same part number, in accordance with Embraer Alert Service Bulletin
170-52-A036 or 190-52-A018, as applicable.
(4) Actions done before May 7, 2007, in accordance with Embraer
Alert Service Bulletin 170-52-A036 or 190-52-A018, both dated March
12, 2007, are acceptable for compliance with the corresponding
requirements of this AD.
Note 1: For the purposes of this AD, a detailed inspection is:
``An intensive examination of a specific item, installation, or
assembly to detect damage, failure, or irregularity. Available
lighting is normally supplemented with a direct source of good
lighting at an intensity deemed appropriate. Inspection aids such as
mirror, magnifying lenses, etc., may be necessary. Surface cleaning
and elaborate procedures may be required.''
Note 2: Embraer Alert Service Bulletins 170-52-A036 and 190-52-
A018 refer to Embraer Service Bulletins 170-50-0006 and 190-50-0006,
respectively, as additional sources of guidance for the rework and
roller fitting cover plate removal. Embraer Alert Service Bulletins
170-50-0006 and 190-50-0006 are currently at Revision 01, dated
March 13, 2007.
Repetitive Inspections for Damage
(i) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: Repeat the inspection specified in paragraph
(h)(3) of this AD at intervals not to exceed 150 flight cycles until
the terminating action specified in paragraph (k)(3) of this AD has
been accomplished.
Parts Installation
(j) For Model ERJ 170-100 LR, -100 STD, -100 SE, -100 SU, -200
LR, -200 STD, and -200 SU airplanes; and ERJ 190-100 STD, -100 LR,
and -100 IGW airplanes: As of May 7, 2007, no person may install a
roller fitting cover plate on the forward and aft cargo door frames
on any airplane.
New Requirements of This AD
Actions and Compliance
(k) Unless already done, do the following actions.
(1) For Model ERJ 190-200 LR, -200 STD, and -200 IGW airplanes:
As of 24 hours after the effective date of this AD, before each
flight after closing the cargo doors, verify that the forward and
aft cargo doors are closed flush with the fuselage skin, and that
all 4 latched and locked indicators at the bottom of each door are
green. Persons qualified to do this verification are mechanics and
flightcrew members. If it cannot be verified that both doors are
closed flush with the fuselage skin, and that all 4 latched and
locked indicators at the bottom of each door are green, repair
before further flight. Repeat the verification before every flight
until accomplishment of the actions required by paragraph (k)(2) of
this AD.
(2) For Model ERJ 190-200 LR, -200 STD, and -200 IGW airplanes:
Within 10 days after the effective date of this AD, do the actions
specified in paragraphs (k)(2)(i), (k)(2)(ii), and (k)(2)(iii) of
this AD, in accordance with the Accomplishment Instructions of
Embraer Alert Service Bulletin 190-52-A018, Revision 01, dated March
23, 2007. Repeat the inspection specified in paragraph (k)(2)(iii)
of this AD at intervals not to exceed 150 flight cycles until the
terminating action specified in paragraph (k)(3) of this AD has been
accomplished.
(i) Remove the roller fitting cover plate on the forward and aft
cargo door frames.
(ii) Perform a detailed inspection of the forward and aft cargo
doors to detect signs of interference between the lock handle and
the aft edge liner assembly. Then rework the aft edge liner assembly
at the applicable time specified in paragraph (k)(2)(ii)(A) or
(k)(2)(ii)(B) of this AD.
(A) If any sign of interference is detected: Rework the assembly
before further flight.
(B) If no sign of interference is detected: Rework the assembly
within 150 flight cycles after the inspection.
(iii) Perform a detailed inspection for signs of damage of the
lateral roller fitting on the forward and aft cargo door frames at
the fuselage. If any damage is found, replace the lateral roller
fitting before further flight with a new roller fitting having the
same part number, in accordance with Embraer Alert Service Bulletin
190-52-A018, Revision 01, dated March 23, 2007.
(3) For all airplanes: Within 5,000 flight cycles after the
effective date of this AD, do the actions specified in paragraphs
(k)(3)(i) and (k)(3)(ii) of this AD on the forward and aft cargo
doors. Accomplishing the actions in this paragraph terminates the
repetitive inspections required by paragraphs (i) and (k)(2) of this
AD.
(i) Relocate the cargo door closed indication sensor in
accordance with the Accomplishment Instructions of Embraer Service
Bulletin 170-52-0041, Revision 01, dated June 13, 2008; or 190-52-
0023, Revision 02, dated March 11, 2008; as applicable.
(ii) Modify the cargo door lock handle mechanism and replace the
forward and aft cargo door roller fittings having part number (P/N)
170-92569-401 and 170-85452-401 with new fittings having P/N 170-
92569-403 and 170-85452-403, as applicable. Do the modification in
accordance with the Accomplishment Instructions of Embraer Service
Bulletins 170-52-0044, dated January 18, 2008; or 190-52-0027, dated
March 20, 2008; as applicable.
(4) Actions done before the effective date of this AD in
accordance with Embraer Service Bulletin 170-52-0041, dated
September 6, 2007; or 190-52-0023, dated September 6, 2007, or
Revision 01, dated December 6, 2007; as applicable; are acceptable
for compliance with the corresponding requirements of this AD.
(5) Within 12 months after the effective date of this AD or 12
months after accomplishing the modification required by paragraph
(k)(3) of this AD, whichever occurs later: Incorporate information
into the maintenance program to include the operational (OPC) and
functional (FNC) checks of the forward and aft cargo doors; in
accordance with a method approved by the
[[Page 58194]]
Manager, International Branch, ANM-116, Transport Airplane
Directorate, FAA; or the Ag[ecirc]ncia Nacional de
Avia[ccedil][atilde]o Civil (or its delegated agent). Within 6,000
flight hours after doing the actions required by paragraph (k)(3) of
this AD, do the OPC and FNC checks and repeat the checks thereafter
at intervals not to exceed 6,000 flight hours.
Note 3: Guidance on the OPC and FNC checks specified in
paragraph (k)(5) of this AD can be found in the document specified
in Table 1 of this AD, as applicable:
Table 1--OPC and FNC Guidance
------------------------------------------------------------------------
Manual-- Task-- Date--
------------------------------------------------------------------------
Embraer 170 Aircraft 52-31-00-710-801-A/ July 15, 2008.
Maintenance Manual. 500.
52-31-20-720-801-A/ July 15, 2008.
500.
52-32-00-710-801-A/ July 15, 2008.
500.
52-32-20-720-801-A/ July 15, 2008.
500.
Embraer 190 Aircraft 52-31-00-710-801-A/ July 15, 2008.
Maintenance Manual. 500.
52-31-20-720-801-A/ July 15, 2008.
500.
52-32-00-710-801-A/ July 15, 2008.
500.
52-32-20-720-801-A/ July 15, 2008.
500.
------------------------------------------------------------------------
Note 4: For the purposes of this AD, a functional check (FNC)
is: ``A quantitative check to determine if one or more functions of
an item perform within specified limits.''
Note 5: For the purposes of this AD, an operational check (OPC)
is: ``A task to determine if an item is fulfilling its intended
purpose. Since it is a failure finding task, it does not require
quantitative tolerances.''
FAA AD Differences
Note 6: This AD differs from the MCAI and/or service
information as follows: Where the MCAI includes a compliance time of
``after accomplishment of the modification'' for revising the
maintenance program for Model ERJ-170 airplanes, we have determined
that a compliance time of ``within 12 months after the effective
date of the AD or within 12 months after accomplishment of the
modification, whichever occurs later'' is appropriate. This
compliance time is equivalent to the compliance time required for
Model ERJ-190 airplanes. The manufacturer and ANAC agree with this
compliance time.
Other FAA AD Provisions
(l) The following provisions also apply to this AD:
(1) Alternative Methods of Compliance (AMOCs): The Manager,
International Branch, FAA, has the authority to approve AMOCs for
this AD, if requested using the procedures found in 14 CFR 39.19.
Send information to ATTN: Kenny Kaulia, Aerospace Engineer,
International Branch, ANM-116, FAA, Transport Airplane Directorate,
1601 Lind Avenue, SW., Renton, Washington 98055-4056; telephone
(425) 227-2848; fax (425) 227-1149. Before using any approved AMOC
on any airplane to which the AMOC applies, notify your principal
maintenance inspector (PMI) or principal avionics inspector (PAI),
as appropriate, or lacking a principal inspector, your local Flight
Standards District Office. The AMOC approval letter must
specifically reference this AD. AMOCs approved previously in
accordance with AD 2007-06-53, are approved as AMOCs for the
corresponding provisions of paragraph (i) of this AD.
(2) Airworthy Product: For any requirement in this AD to obtain
corrective actions from a manufacturer or other source, use these
actions if they are FAA-approved. Corrective actions are considered
FAA-approved if they are approved by the State of Design Authority
(or their delegated agent). You are required to assure the product
is airworthy before it is returned to service.
(3) Reporting Requirements: For any reporting requirement in
this AD, under the provisions of the Paperwork Reduction Act (44
U.S.C. 3501 et seq.), the Office of Management and Budget (OMB) has
approved the information collection requirements and has assigned
OMB Control Number 2120-0056.
Related Information
(m) Refer to Brazilian Airworthiness Directives 2007-03-01R1,
dated June 9, 2008, and 2007-03-02R2, dated November 21, 2008; and
the service information contained in Table 2 of this AD; for related
information.
Table 2--Service Information
------------------------------------------------------------------------
Service bulletin Revision Date
------------------------------------------------------------------------
Embraer Alert Service Bulletin 170- 01 March 23, 2007.
52-A036.
Embraer Alert Service Bulletin 190- 01 March 23, 2007.
52-A018.
Embraer Service Bulletin 01 June 13, 2008.
170[dash]52[dash]0041.
Embraer Service Bulletin \1\ January 18, 2008.
170[dash]52[dash]0044.
Embraer Service Bulletin 02 March 11, 2008.
190[dash]52[dash]0023.
Embraer Service Bulletin \1\ March 20, 2008.
190[dash]52[dash]0027.
------------------------------------------------------------------------
\1\ Original.
Material Incorporated by Reference
(n) You must use the applicable service information contained in
Table 3 of this AD to do the actions required by this AD, unless the
AD specifies otherwise.
Table 3--Material Incorporated by Reference
------------------------------------------------------------------------
Service bulletin Revision Date
------------------------------------------------------------------------
Embraer Alert Service Bulletin 170- 01 March 23, 2007.
52-A036.
Embraer Alert Service Bulletin 190- 01 March 23, 2007.
52-A018.
Embraer Service Bulletin 170-52- 01 June 13, 2008.
0041.
Embraer Service Bulletin 170-52- \1\ January 18, 2008.
0044.
Embraer Service Bulletin 190-52- 02 March 11, 2008.
0023.
[[Page 58195]]
Embraer Service Bulletin 190-52- \1\ March 20, 2008.
0027.
------------------------------------------------------------------------
\1\ Original.
(1) For service information identified in this AD, contact
Empresa Brasileira de Aeronautica S.A. (EMBRAER), Technical
Publications Section (PC 060), Av. Brigadeiro Faria Lima, 2170--
Putim--12227-901 S[atilde]o Jose dos Campos--SP--Brasil; telephone:
+55 12 3927-5852 or +55 12 3309-0732; fax: +55 12 3927-7546; e-mail:
[email protected]; Internet: http://www.flyembraer.com.
(2) You may review copies of the service information at the FAA,
Transport Airplane Directorate, 1601 Lind Avenue SW., Renton,
Washington. For information on the availability of this material at
the FAA, call 425-227-1221 or 425-227-1152.
(3) You may also review copies of the service information that
is incorporated by reference at the National Archives and Records
Administration (NARA). For information on the availability of this
material at NARA, call 202-741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
Issued in Renton, Washington, on October 26, 2009.
Stephen P. Boyd,
Acting Manager, Transport Airplane Directorate, Aircraft Certification
Service.
[FR Doc. E9-26622 Filed 11-10-09; 8:45 am]
BILLING CODE 4910-13-P
Why this text is shown
The complete text was extracted from the official GovInfo HTML edition for this publication. Acquired 2026-10-09T03:19:39.836919+00:00. Text extraction preserves the recorded source wording; it does not determine current requirements.
Open the captured official edition
- Source SHA-256
- d75e3d8f12ab770e85803b280c000ae9e77202002eed5f0b4f729365958c6fde
- Text SHA-256
- 9f8a65a72c4685aa488b3421409a6449c33fc8d31e7e6e98238764babf5a1ac8
Return to the full metadata catalog · Search complete publication text · Explore retained publication text and evidence
Coverage and limits
These are dated publication metadata, recorded clauses and literal source observations. Word, model-label, header and reference matches do not establish current legal effect, manufacturer/model identity, aircraft applicability, installed configuration or compliance.
The collection uses 33 explicit annual source snapshots. Source captures and operative-text qualifications have separate states. Missing information remains unknown.